When you are connected to the barge and are ready to start bunkering, who gave the order to start the pumps?

  1. AThe engineer responsible for bunkering the receiving vessel. ✓
  2. BThe master of the receiving vessel.
  3. CThe master of the bunker barge or shore terminal operator.
  4. DPump man on the barge or shore terminal.

Correct answer: A) The engineer responsible for bunkering the receiving vessel.