When preparing the main switchboard for electricity receiving, what action will we take first?

  1. ACheck with a mega-ohmmeter the status of the board insulation.
  2. BCarry out an external inspection of the MSB for the security that its current parts have no external objects.
  3. CCheck the absence of voltage in the MSB buses. ✓
  4. DCheck that the circuit breakers or other circuit breakers are not turned on.

Correct answer: C) Check the absence of voltage in the MSB buses.