Which statement about the order in which boiler water analysis is performed is false?
- AIt is performed up to twice a day.
- BIt is done after cooling the water, but not later than 4 hours.
- CThe sample is always taken from the same location - the down-purge pipeline. ✓
- DThe pipeline is well blown, the vessels are rinsed with the same water.
Correct answer: C) The sample is always taken from the same location - the down-purge pipeline.