In order to maintain a half-hour readiness of a turboelectric steam power plant, the turbines must:

  1. ATurbines should be continuously heated.
  2. BTurn on the heating every half hour.
  3. CIdle. ✓
  4. DIn half an hour, the operation mode can be reached even with an unheated turbine.

Correct answer: C) Idle.