At what load of the ME the soot blowing of the exhausg gas boiler has to be carried out?

  1. AAt low load .
  2. BAt medium load .
  3. CAt normal pressure.
  4. DAt high load . ✓

Correct answer: D) At high load .

← PreviousNext →
Take the full test: F6 Maintenance and Repair — Management Level →Random exam test generator, free, no registration