SeaQuiz

Which of the listed operations should we perform first before starting an electrical machine that has been idle for a long time?

  1. ALubrication and rotation.
  2. BChecking for forgotten objects inside the machine.
  3. CMeasuring and recording insulation resistance. ✓
  4. DPainting the body of the machine.

Correct answer: C) Measuring and recording insulation resistance.