What is included in the re-testing conducted at the end of the sea trials of the electrical equipment?

  1. AChecking the stores for spare parts and spare parts according to a list from the manufacturer.
  2. BRe-checking of alarms and signaling in ER.
  3. CChecking the readiness of the personnel to work with the electrical part.
  4. DInspection of electrical equipment, which gave defects during sea trials. ✓

Correct answer: D) Inspection of electrical equipment, which gave defects during sea trials.