SeaQuiz

You are on a voyage from Boston, MA, to the South Pass, LA. The distance is 1870 miles, and the speed of advance is 13.6 knots. You estimate 16.5 hours for bunkering enroute at Port Everglades, FL. If you sailed at 0836 hours (ZD +5), 26 February , what was your ETA (ZD +6) at the South Pass?

  1. A2336, 3 March
  2. B1136, 4 March
  3. C1236, 4 March
  4. D1736, 4 March ✓

Correct answer: D) 1736, 4 March

USCG question bank (2008) · Navigation Problems – Question Bank Book 5 · pass mark 70%