SeaQuiz

After cranes have been installed on offshore drilling units the hooks, hook block, slings, rib and other rigging must be load tested. This test must be performed once each __________.

  1. A12 months
  2. B24 months
  3. C36 months
  4. D48 months ✓

Correct answer: D) 48 months

USCG question bank (2008) · Deck Safety – Question Bank Book 4 · pass mark 70%

← PreviousNext →
Take the full practice test: Deck Safety – Question Bank Book 4 →Free USCG practice test with the real pass mark, no sign-up

More questions from this module

Question list: Deck Safety – Question Bank Book 4 (BK4)