The most accurate method for measuring drilling mud required to fill the hole when drill stem is removed is by use of a __________.
- Apit level change
- Bpump stroke count
- Ctrip tank ✓
- Dmud return flow indicator
Correct answer: C) trip tank
Correct answer: C) trip tank