During severe storms when survival becomes a major concern, it may become necessary to relieve high anchor tensions on the windward side of the unit by __________.
- Adeballasting the rig
- Bballasting the rig
- Cpaying out cable on the windward side
- Dpaying out cable on the leeward side ✓
Correct answer: D) paying out cable on the leeward side