When shoring a damaged bulkhead on a MODU, effort should be taken to spread the pressure over the __________.
- Amaximum possible area ✓
- Bminimum possible area
- Cnearest watertight door
- Dnearest longitudinal girder
Correct answer: A) maximum possible area