For a semisubmersible moored in heavy weather conditions, the weather lines should be adjusted so that several lines carry about the same tension, and the leeward lines are __________.
- Atensioned to reduce weather mooring line tensions
- Bpaid out to reduce weather mooring line tensions ✓
- Cadjusted so that at least 1,000 feet of chain lie along the bottom
- Dadjusted so that the vertical component of chain tension at the lower fairlead is not excessive
Correct answer: B) paid out to reduce weather mooring line tensions