A severe storm threatens the COASTAL DRILLER, and a decision is made to evacuate the unit. If practical, all non-essential personnel should be off the unit in advance of the storm's predicted arrival by __________.

  1. A12 hours
  2. B24 hours
  3. C36 hours
  4. D48 hours ✓

Correct answer: D) 48 hours