During a long ocean tow of a jack-up the clearance in the upper guide should be reduced to zero to restrain the leg and eliminate the impact loads from dynamic responses. This is best done by __________.
- Alowering the spud cans below the hull
- Braising the spud cans into hull recesses
- Ctapering the upper guides and building up the teeth ✓
- Dremove certain lengths of leg
Correct answer: C) tapering the upper guides and building up the teeth