During a long ocean tow of a jack-up the clearance in the upper guide should be reduced to zero to restrain the leg and eliminate the impact loads from dynamic responses. This is best done by __________.

  1. Alowering the spud cans below the hull
  2. Braising the spud cans into hull recesses
  3. Ctapering the upper guides and building up the teeth ✓
  4. Dremove certain lengths of leg

Correct answer: C) tapering the upper guides and building up the teeth

USCG question bank (2008) · Deck Safety – Question Bank Book 4 · pass mark 70%