In anticipation of heavy weather, it is decided to deballast the DEEP DRILLER to survival draft. The marine riser should be disconnected, pulled, and laid down. After doing so, the riser tension will be __________.

  1. Azero ✓
  2. Bequal to the weight of the riser
  3. Cdependent on the water depth
  4. Dapplied at the riser tensioner sheaves

Correct answer: A) zero