Assuming that the recommended hatch loading sequence is followed, how many long tons of iron ore may be loaded through hatch No. 1 while using a single belt loader to arrive at a desired mean keel draft of 29'-11"? (use the Guidance Manual for Loading M.V. GRAND HAVEN)

  1. A2230 tons ✓
  2. B2270 tons
  3. C2310 tons
  4. D2350 tons

Correct answer: A) 2230 tons

USCG question bank (2008) · Deck Safety – Question Bank Book 4 · pass mark 70%