SeaQuiz

Your vessel is damaged and is listing to port. The rolling period is short. There is sufficient freeboard so that deck edge submersion is not a problem. What corrective action should be taken FIRST in regard to the vessel's stability?

  1. APress up any slack double-bottom tanks to eliminate free surface
  2. BFlood any empty double-bottom tanks to add weight low and down
  3. CJettison topside weights to reduce KG and KB
  4. DShift any off-center weights from port to starboard ✓

Correct answer: D) Shift any off-center weights from port to starboard

USCG question bank (2008) · Deck Safety – Question Bank Book 4 · pass mark 70%

← PreviousNext →
Take the full practice test: Deck Safety – Question Bank Book 4 →Free USCG practice test with the real pass mark, no sign-up

More questions from this module

Question list: Deck Safety – Question Bank Book 4 (BK4)