SeaQuiz

Which topic is NOT required to be discussed at the pre-transfer conference?

  1. AIdentity of the product to be transferred
  2. BDetails of transferring and receiving systems
  3. CEmergency shutdown procedures
  4. DEstimated time of finishing cargo ✓

Correct answer: D) Estimated time of finishing cargo

USCG question bank (2008) · Deck Safety – Question Bank Book 4 · pass mark 70%