The charterer has completed loading the vessel in 3 days instead of the 5 days agreed to in the charter party. As a result of this, the __________.
- Ashipowner may charge for two lay days
- Bcharterer may receive dispatch money ✓
- Cstevedore may collect demurrage
- Dconsignee may be required to pay a ceaser fee
Correct answer: B) charterer may receive dispatch money