SeaQuiz

When a tank vessel with a capacity of 250 barrels is transferring oil to a facility, the Pollution Prevention Regulations (33 CFR), require an emergency means to stopping the flow of oil which must be operable from __________.

  1. Atwo or more locations on the tank vessel
  2. Ba remote location of equal distance from the tank vessel and facility
  3. Cthe usual operating station of the person in charge of the oil transfer ✓
  4. Dthe engine room, cargo control room and bridge sequentially

Correct answer: C) the usual operating station of the person in charge of the oil transfer

USCG question bank (2008) · Engineering Safety – Question Bank Book 15 · pass mark 70%

← PreviousNext →
Take the full practice test: Engineering Safety – Question Bank Book 15 →Free USCG practice test with the real pass mark, no sign-up

More questions from this module

Question list: Engineering Safety – Question Bank Book 15 (BK15)