"Line Displacement" is a procedure that is followed at an oil terminal facility, when there is a change of __________.
- Acargo lines at the terminal before loading
- Bproduct before the start of loading
- Cproduct during the final phase of loading ✓
- Dproduct after the final discharge
Correct answer: C) product during the final phase of loading