While standing watch in the engine room, which of the following actions should be taken to reestablish a 'blown' air ejector loop seal?

  1. ADecrease the steam pressure to the air ejector nozzles.
  2. BShut off the steam to the second stage air ejector momentarily then open it again.
  3. CMomentarily close the valve in the loop seal line, then reopen slowly. ✓
  4. DIncrease the condensate flow through the air ejector.

Correct answer: C) Momentarily close the valve in the loop seal line, then reopen slowly.

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%