SeaQuiz

The most critical period of main turbine operation is during cold start-up, rather than hot shutdown because __________.

  1. Alubricant film thickness during start-up is considerably less than the dimensions of gear surface irregularities
  2. Bdifferential expansion can result from the temperature difference between the rotor and rotor casing ✓
  3. Cthe danger of blade erosion damage from dry steam impingement is greater during start-up
  4. Dharmonic vibrations associated with critical speed can easily be reached during start-up

Correct answer: B) differential expansion can result from the temperature difference between the rotor and rotor casing