A set of first and second stage air ejectors are used with a large sea water cooled steam condenser. If the first stage air ejector is not in operation __________.
I. vacuum can not be established
II. maximum operating vacuum can not be maintained

  1. AI only
  2. BII only ✓
  3. CBoth I and II
  4. DNeither I nor II

Correct answer: B) II only