The vent line from the main condenser water boxes was not opened when the waterside was recharged. This would __________.
I. lead to a build up of pressure on the tube sheet of greater than 40 psig.
II. prevent the design vacuum from being attained under normal operating conditions at sea.
- AI only
- BII only ✓
- CBoth I and II
- DNeither I nor II
Correct answer: B) II only