SeaQuiz

To raise vacuum on the main turbine unit, you should __________.

  1. Astart the lube oil pump after starting the jacking gear
  2. Bwarm up and drain the main steam lines
  3. Cpump the main condenser hotwell dry
  4. Dadmit gland sealing steam to the turbine glands ✓

Correct answer: D) admit gland sealing steam to the turbine glands

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%

← PreviousNext →