The FIRST step in breaking vacuum on a main turbine unit should be to __________.

  1. Asecure the steam to the main air ejector ✓
  2. Bsecure the steam to the gland seal system
  3. Cstop the main circulating pump
  4. Dstop the main condensate pump

Correct answer: A) secure the steam to the main air ejector

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%