The jacking gear must be engaged as quickly as possible when securing the main turbines in order to __________.

  1. Apermit rapid cooling of the reduction gears
  2. Bprevent uneven cooling of the turbine rotors ✓
  3. Cmaintain a constant supply of lube oil to the main unit
  4. Dprevent the stern tube bearing from overheating

Correct answer: B) prevent uneven cooling of the turbine rotors