In order for a maximum number of boiler generating and circulating tubes to be installed without weakening the tube sheet, which of the listed procedures should be carried out?

  1. AAll rows of tubes should be bent at the same angle.
  2. BAll rows of tubes should be installed horizontal to the drum.
  3. CDifferent rows of tubes should be bent to enter the drum at any convenient angle.
  4. DAll tubes should be installed normal to the drum surfaces. ✓

Correct answer: D) All tubes should be installed normal to the drum surfaces.