The jacking gear is used in preparation for starting a marine turbine and reduction gear unit to __________.

  1. Aallow the rotor to cool evenly
  2. Ballow a film of oil to form on the spring bearings
  3. Cprevent the gland seal steam from distorting the rotor ✓
  4. Dlisten for rubbing noises from the gland seal condenser

Correct answer: C) prevent the gland seal steam from distorting the rotor

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%