When a high pressure turbine is operating at sea speed, the pressure of the steam leaking through the shaft gland packing may be slightly higher than the pressure setting of the gland seal regulator. In this situation, the excess steam at the regulator is directed to the __________.

  1. Agland exhaust condenser
  2. Bexcess steam condenser
  3. Cmain condenser ✓
  4. Dauxiliary exhaust system

Correct answer: C) main condenser

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%