In a cross-compound main propulsion unit, the astern turbine is usually installed at the __________.

  1. Alow pressure end of the low pressure turbine ✓
  2. Bhigh pressure end of the low pressure turbine
  3. Clow pressure end of the high pressure turbine
  4. Dhigh pressure end of the high pressure turbine

Correct answer: A) low pressure end of the low pressure turbine

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%