If while filling the boiler a newly installed gasket on a water-tube handhole plate weeps, you should __________.

  1. Acoat the gasket with graphite
  2. Bretighten the stud nut with an air wrench
  3. Cuse a double gasket
  4. Dcenter and tighten with correct size wrench ✓

Correct answer: D) center and tighten with correct size wrench

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%