When preparing to cut a boiler in on the line, you determine that the steam pressure of the incoming boiler is about 5 psig above line pressure. Which of the following steps should you take next?

  1. AOpen the superheater vent.
  2. BLight off additional burners.
  3. COpen the desuperheated steam stop. ✓
  4. DTest the hand relieving gear.

Correct answer: C) Open the desuperheated steam stop.

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%