Before placing the jacking gear in operation on a main turbine unit, you must always insure that __________.

  1. Athe gland seal steam system is operating
  2. Bthe main salt water circulating pump is operating
  3. Cthe condensate system is operating
  4. Dthe main lube oil system is operating ✓

Correct answer: D) the main lube oil system is operating

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%