The purpose of the reaction turbine dummy piston is to ________.

  1. Acounteract and balance axial thrust produced by the turbine rotor ✓
  2. Bact in conjunction with gland seal steam to balance turbine thrust
  3. Cassist in maintaining radial clearances
  4. Deliminate radial thrust caused by the pressure increases in the turbine stages

Correct answer: A) counteract and balance axial thrust produced by the turbine rotor