Which of the listed procedures should be followed when raising vacuum on the main propulsion plant prior to getting underway?

  1. AStart the condensate and circulating pumps, engage the turning gear, start the lube oil system, then start the first-and second-stage air ejectors and the gland sealing.
  2. BStart the condensate and circulating pumps, start the lube oil system, start the air ejectors and the gland sealing system, and engage the turning gear.
  3. CStart the lube oil system, engage the turning gear, start the condensate and circulating pumps, start the gland sealing system and second-stage air ejector. ✓
  4. DStart the lube oil system, start the second-stage air ejector and the gland sealing system, start the condensate and circulating pumps, and start the turning gear.

Correct answer: C) Start the lube oil system, engage the turning gear, start the condensate and circulating pumps, start the gland sealing system and second-stage air ejector.

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%