According to 46 CFR Part 61, which of the following statements is true concerning the inspection of water-tube boilers?

  1. AAll mountings shall be opened up and examined by a Coast Guard inspector at eight year intervals after the initial inspection.
  2. BAll boiler mounting studs or bolts shall be removed for examination by a Coast Guard inspector every 4 years after initial inspection.
  3. CBoiler mountings attached to boiler nozzles must be opened and removed for examination every 8 years.
  4. DBoiler mountings attached directly to the boiler plating by screwed studs and nuts shall be removed and examined every 10 years. ✓

Correct answer: D) Boiler mountings attached directly to the boiler plating by screwed studs and nuts shall be removed and examined every 10 years.

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%