Guardian valves are installed on main propulsion turbines to __________.

  1. Aprevent steam from leaking into the astern element while the vessel is maneuvering
  2. Bprovide an emergency means of quickly closing the throttle
  3. Cprovide a means to supply steam directly to the astern element of the turbine
  4. Dprevent steam from leaking into the astern element while at full sea speed ✓

Correct answer: D) prevent steam from leaking into the astern element while at full sea speed

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%