With vacuum up and the main propulsion turbine standing by while awaiting engine orders, it is necessary to roll the unit alternately ahead and astern every five minutes to __________.

  1. Adistribute the gland sealing steam evenly throughout the glands
  2. Bslowly bring the lube oil and bearings to operating temperature
  3. Cwarm the astern guarding valve and the low lube oil pressure throttle trip
  4. Dreduce the possibility of warping the turbine rotors ✓

Correct answer: D) reduce the possibility of warping the turbine rotors

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%