The pressure drop existing across the diaphragm of a pressure compounded impulse turbine necessitates __________.

  1. Ainstallation of a dummy piston and equalizing line to reduce thrust
  2. Binstallation of a diaphragm packing seal to minimize interstage leakage ✓
  3. Ccircumferential dovetailing to secure the rotor blades
  4. DSeal stripping the tips of the turbine blades

Correct answer: B) installation of a diaphragm packing seal to minimize interstage leakage

USCG question bank (2008) · Steam Plants – Question Bank Book 13 · pass mark 70%